Liquid Granite | Application method
Professional Installation Sequence
Ready for use in about 2 days — full hardness in 7 days.

01
Surface Grinding
Mechanically grind the concrete to remove laitance, weak layers and contamination.

02
Dust Removal
Vacuum thoroughly until the substrate is clean, dry and dust-free.

03
Primer Application
Apply WERKON Primer (Liquid Granite R) evenly by roller and avoid puddles.

04
Add Part B to Part A
Pour the complete pre-measured Part B into Part A. Use full packs only.

05
Mechanical Mixing
Mix with a slow-speed paddle for approx. 3 minutes until homogeneous.

06
Pour onto the Floor
Pour the mixed material immediately in a continuous ribbon over the primed floor.

07
Spread with Steel Trowel
Pull and level the wet material to the specified thickness.

08
De-air with Spiked Roller
Use a spiked roller within the working time. Wear spike shoes on the wet floor.
Liquid Granite | Application method
Ready for use in about 2 days — full hardness in 7 days.
Day 0
Application
≈ 8 h
Initial setting
≈ 24 h
Final setting
≈ 2 days
Ready for use
7 days
Full hardness
Designed for trained hands, not rare artists.
Much easier to apply than conventional decorative resin floors, with no need for rare artistic skills. A trained applicator can deliver a perfect result.
Floors that perform longer.